Another `Road Closure` message forwarded by David Shearan - The following email arrived this morning.
"Apologies for the confusion.
We were unable to start yesterday as there was a conflict between works there was an urgent Severn Trent closure in Grimpo which was using Ruyton as a diversion route.
The work is planned to go ahead today and tomorrow however there is BT works planned on Church Street Friday that is restricting our work to two days. I have asked permitting whether an extension would be possible Friday if necessary.
The team are commencing work this morningstarting at the bridge".
I hope this clarifies matters.